Kanakkuമലയാളം
Public WorksApproved

Construction of Kalikkadavu bridge across Chaitravahini puzha, Madakkal kadavu Bridge & Padanna Thekkekadavu Hanging bridge in Kasaragod District

Approved by KIIFB

₹89.7 crore

₹89,69,55,014

Paid so far

₹2.36 crore

₹2,36,30,111 · 2.6% of the amount approved

Works

7

₹2.36 crore paid across the works

Works (7)

2016-17-Construction of bridge at Kalikkadavu across Chaithravahini river in Kasaragod district - Contract

Work awarded
₹1.96 crorepaid
₹5.68 croreapproved

2016-17-Construction of bridge at Kalikkadavu across Chaithravahini river in Kasaragod district - KSEB

Work awarded
₹9.28 lakhpaid
₹9.28 lakhapproved

2016-17-Construction of bridge at Kalikkadavu across Chaithravahini river in Kasaragod district - KWA

Work awarded
₹1.69 lakhpaid
₹1.69 lakhapproved

Construction of Kalikkadavu bridge across Chaitravahini puzha, Madakkal kadavu Bridge & Padanna Thekkekadavu Hanging bridge in Kasaragod District- Madakkal Bridge LA & RR package

Work awarded
₹14.25 lakhpaid
₹2.81 croreapproved

Construction of Kalikkadavu bridge across Chaitravahini puzha, Madakkal kadavu Bridge & Padanna Thekkekadavu Hanging bridge in Kasaragod District- Thekkekadavu Hanging Bridge LA & RR package

Work awarded
₹7.21 lakhpaid
₹1.29 croreapproved

Madakkal Bridge across Valiyaparamba back water in Kasaragod district? CRZ Clearance including Rapid EIA study Package

Work awarded
₹3.72 lakhpaid
₹27.87 lakhapproved

Thekkekadu bridge and approach road across Kavvayi river in Kasaragod District? CRZ Clearance including Rapid EIA study package.

Work awarded
₹3.72 lakhpaid
₹27.87 lakhapproved

Total of the works: ₹10,44,43,847 approved, ₹2,36,30,111 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
Construction of 11 Bridges
KIIFB status
Approved
Name as KIIFB publishes it
PWD008-07: Construction of Kalikkadavu bridge across Chaitravahini puzha, Madakkal kadavu Bridge & Padanna Thekkekadavu Hanging bridge in Kasaragod District

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026