Kanakkuമലയാളം
Public WorksApproved

2017-18 Construction of Pattambi Bridge in Palakkad District

Approved by KIIFB

₹52.59 crore

₹52,58,59,404

Paid so far

₹7.18 crore

₹7,17,96,598 · 13.7% of the amount approved

Works

2

₹7.18 crore paid across the works

Works (2)

2017-18 Construction of Pattambi Bridge in Palakkad District - LA

Work awarded
₹45.37 lakhpaid
₹11.45 croreapproved

Construction of Pattambi Bridge in Palakkad District - Contract work

Work awarded
₹6.73 crorepaid
₹39.11 croreapproved

Total of the works: ₹50,56,35,267 approved, ₹7,17,96,598 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
69 Bridges
KIIFB status
Approved
Name as KIIFB publishes it
KIIFB 2017-18 Construction of Pattambi Bridge in Palakkad District

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
30-09-2026
Works last checked
02-10-2026
First recorded
30-09-2026