Public WorksApproved

Construction of Azhikode-Munambam Bridge in Thrissur District

Approved by KIIFB

₹200.15 crore

₹2,00,14,68,922

Paid so far

₹143.61 crore

₹1,43,60,61,085 · 71.8% of the amount approved

Works

5

₹143.61 crore paid across the works

Works (5)

AZHIKODE-MUNAMBAM BRIDGE- Land acquisition

Work awarded
₹10.22 crorepaid
₹14.62 croreapproved

Construction of Azhikode-Munambam Bridge in Thrissur District-KSEB Utility shifting

Work awarded
₹40.7 lakhpaid
₹40.7 lakhapproved

Onstruction of Azhikode-Munambam Bridge in Thrissur District - KWA Utility shifting

Work awarded
₹25.56 lakhpaid
₹25.56 lakhapproved

Project - PWDO16-04: 'Construction of Azhikode - Munambam Bridge in Thrissur District- CRZ Clearance including Rapid EIA study Category

Work awarded
₹30.84 lakhpaid
₹33.22 lakhapproved

Total of the works: ₹1,84,68,53,683 approved, ₹1,43,60,61,085 paid.

Details

Department
Public Works
Implementing agency (SPV)
Kerala Road Fund Board (KRFB)
Announced under
69 Bridges
KIIFB status
Approved
Name as KIIFB publishes it
CONSTRUCTION OF AZHIKODE-MUNAMBAM BRIDGE IN THRISSUR DISTRICT

Source

Source
KIIFB project statuskiifb.org/prjStatus.jsp
Amounts retrieved
04-10-2026
Works last checked
04-10-2026
First recorded
30-09-2026

The same project on the map dashboard

KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.

Recorded changes

RetrievedFieldBefore → after
04-10-2026work[CONSTRUCTION OF AZHIKODE-MUNAMBAM BRIDGE IN THRISSUR DISTRICT - Contract].paid_amount1219669852 → 1324128869
04-10-2026paid_amount1331602068 → 1436061085