AZHIKODE-MUNAMBAM BRIDGE- Land acquisition
Work awarded₹10.22 crorepaid
₹14.62 croreapproved
₹200.15 crore
₹2,00,14,68,922
₹133.16 crore
₹1,33,16,02,068 · 66.5% of the amount approved
5
₹133.16 crore paid across the works
Total of the works: ₹1,84,68,53,683 approved, ₹1,33,16,02,068 paid.
KIIFB's two pages share no identifier. We joined these because the approved amount, department and implementing agency are the same.