Bridge work at Railway Portion for Purayar ROB
Work awarded₹11.36 lakhpaid
₹11.36 lakhapproved
₹53.71 crore
₹53,70,63,978
₹12.52 crore
₹12,51,92,436 · 23.3% of the amount approved
5
₹12.52 crore paid across the works
KIIFB's figures do not agree here: its list says ₹53,70,63,978 was approved for the project, while the approvals of the works add up to ₹63,41,38,010. Both are shown as the source states them.
Total of the works: ₹63,41,38,010 approved, ₹12,51,92,436 paid.
| Retrieved | Field | Before → after |
|---|---|---|
| 27-10-2026 | work[Design and Construction of Purayar ROB].paid_amount | 8380360 → 0 |
| 27-10-2026 | paid_amount | 133572796 → 125192436 |
| 10-10-2026 | work[Design and Construction of Purayar ROB].paid_amount | 0 → 8380360 |
| 10-10-2026 | paid_amount | 125192436 → 133572796 |