Note: these figures were last checked against the source 2 days ago. Status

Who must repair it

When PWD finishes a road or a building, the contractor stays liable for a set period to repair defects at their own cost. These are the works inside that period, as PWD lists them.

Works under liability now

161

162 works on the list in all

Liability ends within 90 days

20

After that, repairs fall to the public purse.

Contractors

53

Names as PWD publishes them.

If you see a defect: If a work on this list fails inside its period, PWD can make the contractor put it right. Report it to PWD; its own list names the office responsible for each work. PWD's list

The district is that of the PWD office handling the work; some offices also look after works in neighbouring districts.

  1. Construction of parallel bridge in the downstream of Kovilkkadavu bridge in kanthallor marayoor road km 10/900Bridges · Brdges Sub Division PainavuP T BinoyLiable from 08-12-2022 until 08-12-2027
  2. Kallarkutty Restoration Works-FDW 2018-19 Reconstruction of Retaining wall and drainage facility to approach road of Kallarkutty Bridge.Bridges · Brdges Sub Division PainavuM s Kanjiramkunnel ConstructionsLiable from 14-02-2023 until 14-02-2028

Contractors with the most works

Counted by works now under liability. We treat different spellings of a name as one; two people with the same name may have been counted together.

All contractors

Source

Source: the Kerala Public Works Department's DLP work list, which we read once a week. We do not keep or show the phone numbers printed on PWD's pages. The agreed amount sits in the code of PWD's page without being displayed there, so it may be provisional or out of date; PWD has filled it in for only 1 of the 161 works now under liability.