Kanakkuമലയാളം

Spent on this package so far

₹1.04 crore

₹1,04,04,021

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹10,00,00,000Estimate of sub-project GED005-40, shared by 4 contract packages
Expenditure reported · this package
₹1,04,04,021
Expenditure reported · all 4 packages
₹11,72,40,813117.2% of the estimated amount

Details

Project code
GED005-40-02
Department
General Education
Constituency
AranmulaMLA: Smt. Veena George

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project