Kanakkuമലയാളം

Spent on this package so far

₹5.55 crore

₹5,55,11,379

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹10,00,00,000Estimate of sub-project GED005-42, shared by 2 contract packages
Expenditure reported · this package
₹5,55,11,379
Expenditure reported · all 2 packages
₹10,09,47,439100.9% of the estimated amount

Details

Project code
GED005-42-02
Department
General Education
Constituency
ChengannurMLA: Shri Saji Cherian

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project