This package
Work awarded₹2.67 crorepaid
₹3.41 croreapproved
₹2.09 crore
₹2,09,03,659
KIIFB status: WBS Base One Approved · How we group
On KIIFB's project status page this belongs to “Kasaragod, Kannur, Kozhikode, Palakkad, Malappuram & Trivandrum Cluster”. The figures below are for that whole project, not this package alone.
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
The KIIFB dashboard does not publish these for this project: