Spent on this package so far

₹2.85 crore

₹2,84,84,755

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Money trail

Estimated amount
₹12,00,00,000Estimate of sub-project GED008-06, shared by 4 contract packages
Expenditure reported · this package
₹2,84,84,755
Expenditure reported · all 4 packages
₹11,86,45,84098.9% of the estimated amount

Details

Project code
GED008-06-01
Department
General Education
Constituency
DevikulamMLA: Shri A. Raja

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026