GVHSS Karakurissi - Additional Vhse Block
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Technical Sanction Created · How we group
Money trail
- Estimated amount
- ₹11,84,00,000Estimate of sub-project GED008-28, shared by 5 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 5 packages
- ₹8,82,95,34774.6% of the estimated amount
Details
- Project code
- GED008-28-05
- Department
- General Education
- Executing agency
- WAPCOS Limited
- Constituency
- KongadMLA: Smt. Santhakumari. K
- Name as KIIFB publishes it
- GVHSS KARAKURISSI - ADDITIONAL VHSE BLOCK
What KIIFB approved and paid
On KIIFB's project status page this belongs to “PALAKKAD-KANNUR-KASARGODE CLUSTER-Phase-7”. The figures below are for that whole project, not this package alone.
- Approved
- ₹11,84,00,000₹11.84 crore
- Paid so far
- ₹9,17,64,60277.5% of the amount approved
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Government Higher Secondary School, Chalissery ₹2.89 crore spent
- GHSS Koduvayur ₹2.87 crore spent
- Government Vocational Higher Secondary School, Malampuzha ₹1.8 crore spent
- Government Higher Vocational Secondary School, Karakurissi ₹1.28 crore spent