Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹70,03,33,837Estimate of sub-project HFW002-03, shared by 5 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 5 packages
₹32,92,50,14947% of the estimated amount

Details

Project code
HFW002-03-02
Department
Health & Family Welfare
Constituency
UdumbancholaMLA: Shri M. M. Mani

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Upgradation of Taluk Hospital Nedumkandam-Phase I”. The figures below are for that whole project, not this package alone.

Approved
₹70,03,33,837₹70.03 crore
Paid so far
₹37,95,80,13154.2% of the amount approved

This package

Work awarded
₹58.71 lakhpaid
₹2.11 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project