Electrical and ELV works
Estimated amount
Not published
No figure is published for this package alone.
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: Design Basis Report Created · How we group
Money trail
- Estimated amount
- ₹62,19,85,042Estimate of sub-project HFW002-14, shared by 6 contract packages
- Expenditure reported · this package
- Not published
- Expenditure reported · all 6 packages
- ₹24,67,12,31039.7% of the estimated amount
Details
- Project code
- HFW002-14-08
- Department
- Health & Family Welfare
- Executing agency
- Kerala State Housing Board
- Constituency
- VaikomMLA: Smt. C. K Asha
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Development of Government Taluk Hospital, Vaikom”. The figures below are for that whole project, not this package alone.
- Approved
- ₹62,19,85,042₹62.2 crore
- Paid so far
- ₹27,10,23,48543.6% of the amount approved
Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
- Expenditure so far
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Taluk Hospital Vaikom(Civil works) ₹23.73 crore spent
- Development of Government Taluk Hospital, Vaikom - Lift Works ₹74.74 lakh spent
- Development of Government Taluk Hospital, Vaikom - Firefighting Works ₹19.7 lakh spent
- Development of Government Taluk Hospital, Vaikom - STP works Not published
- Evelopment of Government Taluk Hospital, Vaikom - HVAC works Not published