Estimated amount

₹1,516.76 crore

₹15,16,75,76,632 · ₹556.33 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Money trail

Estimated amount
₹15,16,75,76,632₹1,516.76 crore
Expenditure reported
₹5,56,33,03,07736.7% of the estimated amount

Details

Project code
ITD002-01-01
Department
Information Technology
Name as KIIFB publishes it
KERALA FIBRE OPTIC NETWORK

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Kerala Fibre Optic Network”.

Approved
₹15,16,75,76,632₹1,516.76 crore
Paid so far
₹7,15,90,73,50747.2% of the amount approved

This package

Work awarded
₹578.01 crorepaid
₹1,378.54 croreapproved

Source: KIIFB project status (kiifb.org). Checked 01-10-2026. How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress

Source