Upgradation of Govt ITI Chengannur
Spent on this package so far
₹21.86 crore
₹21,85,92,012
Stage
- Preparation
- Technical sanction
- Tender
- Contract
- Work plan
KIIFB status: WBS Base One Approved · How we group
Money trail
- Estimated amount
- ₹23,66,63,231Estimate of sub-project LBR002-02, shared by 2 contract packages
- Expenditure reported · this package
- ₹21,85,92,012
- Expenditure reported · all 2 packages
- ₹21,85,92,01292.4% of the estimated amount
Details
- Project code
- LBR002-02-01
- Department
- Labour & Skills
- Executing agency
- Kerala Academy for Skills Excellence
- Constituency
- ChengannurMLA: Shri Saji Cherian
What KIIFB approved and paid
On KIIFB's project status page this belongs to “Upgradation of Govt. ITI Chengannur”. The figures below are for that whole project, not this package alone.
- Approved
- ₹23,66,63,231₹23.67 crore
- Paid so far
- ₹22,82,64,22496.5% of the amount approved
Source: KIIFB project status (kiifb.org). How we joined the two sources
What we don't know yet
The KIIFB dashboard does not publish these for this project:
- Contractor, contract amount, scheduled dates, payments and physical progress
Source
- Source
- KIIFB integrated dashboardgis.kiifb.org
- Retrieved
- 30-09-2026
- First recorded
- 30-09-2026
- SHA-256
- 04a00101b9212117…
Other packages under the same sub-project
- Energization works by KSEB at Govt. ITI Chengannur Not published