Kanakkuമലയാളം
LBR002-04-03 Trikaripur

Upgradation of Ek Nayanar Memorial ITI Kayyur

Estimated amount

Not published

No figure is published for this package alone.

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base Zero Approved · How we group

Location

Money trail

Estimated amount
₹13,73,58,655Estimate of sub-project LBR002-04, shared by 3 contract packages
Expenditure reported · this package
Not published
Expenditure reported · all 3 packages
₹6,61,46,77048.2% of the estimated amount

Details

Project code
LBR002-04-03
Department
Labour & Skills
Constituency
TrikaripurMLA: Shri M. Rajagopalan
Name as KIIFB publishes it
UPGRADATION OF EK NAYANAR MEMORIAL ITI KAYYUR

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Upgradation of Govt ITI Koyilandy, Govt ITI Kannur and Ek Nayanar Memorial ITI Kayyur”. The figures below are for that whole project, not this package alone.

Approved
₹13,73,58,655₹13.74 crore
Paid so far
₹6,92,89,89850.4% of the amount approved

Source: KIIFB project status (kiifb.org). How we joined the two sources

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor, contract amount, scheduled dates, payments and physical progress
  • Expenditure so far

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project