Nedumbrakkadu bridge
Completed100%Physical progress
80.5%Financial progress
Scheduled start01-08-2019
Scheduled completion19-05-2025
- Contractor
- M/s Contour Constructions Pvt Ltd
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹20,37,53,065₹20.38 crore
- Amount paid
- ₹16,39,59,040₹16.4 crore
- Paid to contractor
- ₹15,17,63,381₹15.18 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹21,77,90,204₹21.78 crore
- Technical sanction (TS)
- ₹8,04,100₹8.04 lakh
- Tender amount
- ₹20,37,90,703₹20.38 crore
- Letter of acceptance (LOA)
- ₹20,37,90,703₹20.38 crore
- Current progress
- Abutment wall , 5 Span beam 13/15 completed.P4 A2 slab work completed.Tripple box culvert slab completed. Single span precast girder placing completed.Expert committee meeting conducted on 07/07/22.SIA report approved by DC on 25/07/22 , direction for 11