Total of works

₹28.6 crore

₹28,59,95,435

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kozhencherry Bridge

Scheduled completion was 13-01-2026. That was 262 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kozhencherry Bridge

In progress
54%Physical progress
36.5%Financial progress
Scheduled start14-03-2024
Scheduled completion13-01-2026
Implementing agency (SPV)
KRFB
Contract amount
₹19,73,78,393₹19.74 crore
Amount paid
₹7,20,80,920₹7.21 crore
Paid to contractor
₹6,74,99,475₹6.75 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹28,59,95,435₹28.6 crore
Technical sanction (TS)
₹16,45,07,110₹16.45 crore
Tender amount
₹19,73,78,393₹19.74 crore
Current progress
All 52 piles were completed. Also 7 pile caps and works of abutment a2 open foundation completed. Pier and pier cap works of p1,p2,p3,p4,p5,p6 completed.A1 and A2 abutment wall fully completed.In P1-P2 and P4-P5 span, beam, slab arch and macalloy stressi

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹28,59,95,435₹28.6 crore

Details

Project code
PWD001-10-04
Department
Public Works
Constituency
Aranmula

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…