Kozhencherry Bridge
In progress54%Physical progress
36.5%Financial progress
Scheduled start14-03-2024
Scheduled completion13-01-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,73,78,393₹19.74 crore
- Amount paid
- ₹7,20,80,920₹7.21 crore
- Paid to contractor
- ₹6,74,99,475₹6.75 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹28,59,95,435₹28.6 crore
- Technical sanction (TS)
- ₹16,45,07,110₹16.45 crore
- Tender amount
- ₹19,73,78,393₹19.74 crore
- Current progress
- All 52 piles were completed. Also 7 pile caps and works of abutment a2 open foundation completed. Pier and pier cap works of p1,p2,p3,p4,p5,p6 completed.A1 and A2 abutment wall fully completed.In P1-P2 and P4-P5 span, beam, slab arch and macalloy stressi