Arangattukadavu Bridge
Completed100%Physical progress
84.1%Financial progress
Scheduled start28-09-2020
Scheduled completion24-12-2024
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹9,11,77,653₹9.12 crore
- Amount paid
- ₹7,66,59,627₹7.67 crore
- Paid to contractor
- ₹7,17,00,852₹7.17 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹20,35,53,221₹20.36 crore
- Technical sanction (TS)
- ₹9,13,29,259₹9.13 crore
- Tender amount
- ₹8,68,69,132₹8.69 crore
- Letter of acceptance (LOA)
- ₹8,68,69,132₹8.69 crore
- Current progress
- Bridge construction in progress. Substructure completed. Girder construction work completed.Cross beam work in progess. Approach road retaining wall work inon going.