Padaharam Bridge
In progress98.1%Physical progress
91.3%Financial progress
Scheduled start29-06-2020
Scheduled completion31-08-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹60,92,16,997₹60.92 crore
- Amount paid
- ₹52,82,41,686₹52.82 crore
- Paid to contractor
- ₹48,91,65,146₹48.92 crore
- Administrative sanction (AS)
- ₹30,00,00,000₹30 crore
- Financial sanction (FS)
- ₹65,50,95,617₹65.51 crore
- Technical sanction (TS)
- ₹58,74,68,609₹58.75 crore
- Tender amount
- ₹57,83,89,321₹57.84 crore
- Letter of acceptance (LOA)
- ₹57,83,89,321₹57.84 crore
- Current progress
- 35m span Girder 3/6 completed. Culvert work(At takazhi side) completed. 1 no.45m box girder shuttering work in progress.Concent for RR package submitted on 17/05/22.LA fund request of Rs-2.26Cr submitted to TL on 06/06/22