Construction of Padaharam Bridge across Pampa river in Alappuzha District - Balance work - Contract

Spent on this package so far

₹51.89 crore

₹51,88,50,390

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Flags (1)

Overdue · Padaharam Bridge

Scheduled completion was 31-08-2025. That was 397 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Padaharam Bridge

In progress
98.1%Physical progress
91.3%Financial progress
Scheduled start29-06-2020
Scheduled completion31-08-2025
Implementing agency (SPV)
KRFB
Contract amount
₹60,92,16,997₹60.92 crore
Amount paid
₹52,82,41,686₹52.82 crore
Paid to contractor
₹48,91,65,146₹48.92 crore
Administrative sanction (AS)
₹30,00,00,000₹30 crore
Financial sanction (FS)
₹65,50,95,617₹65.51 crore
Technical sanction (TS)
₹58,74,68,609₹58.75 crore
Tender amount
₹57,83,89,321₹57.84 crore
Letter of acceptance (LOA)
₹57,83,89,321₹57.84 crore
Current progress
35m span Girder 3/6 completed. Culvert work(At takazhi side) completed. 1 no.45m box girder shuttering work in progress.Concent for RR package submitted on 17/05/22.LA fund request of Rs-2.26Cr submitted to TL on 06/06/22

Money trail

Estimated amount
₹65,50,95,617Estimate of sub-project PWD001-18, shared by 3 contract packages
Expenditure reported · this package
₹51,88,50,390
Expenditure reported · all 3 packages
₹51,88,50,39079.2% of the estimated amount

Details

Project code
PWD001-18-05
Department
Public Works
Constituency
KuttanadMLA: Shri Thomas K Thomas

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of Padaharam Bridge across Pampa river in Alappuzha District”. The figures below are for that whole project, not this package alone.

Approved
₹65,50,95,617₹65.51 crore
Paid so far
₹57,42,43,98587.7% of the amount approved

This package

Work awarded
₹54.58 crorepaid
₹60.92 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…

Other packages under the same sub-project