Punnamada Bridge
In progress17.3%Physical progress
18.5%Financial progress
Scheduled start10-08-2024
Scheduled completion09-08-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹52,21,22,246₹52.21 crore
- Amount paid
- ₹9,66,66,147₹9.67 crore
- Paid to contractor
- ₹9,05,22,079₹9.05 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹57,40,73,886₹57.41 crore
- Technical sanction (TS)
- ₹47,47,04,037₹47.47 crore
- Tender amount
- ₹52,21,22,246₹52.21 crore
- Current progress
- Estimate for revised FS submitted For Rs.51.59Cr on 03/12/21.Revised estimate to be corrected as per new dierection from KIIFB.LA.SIA study hearing conducted on 16/05/22.Final report of SIA study submitted on 13/06/22.Expert committee meeting conducted o