Njettara Bridge
Completed100%Physical progress
70.1%Financial progress
Scheduled start21-02-2022
Scheduled completion31-12-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹13,49,09,907₹13.49 crore
- Amount paid
- ₹10,12,40,215₹10.12 crore
- Paid to contractor
- ₹9,48,05,428₹9.48 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹15,27,56,833₹15.28 crore
- Technical sanction (TS)
- ₹12,50,00,000₹12.5 crore
- Tender amount
- ₹14,44,26,515₹14.44 crore
- Letter of acceptance (LOA)
- ₹12,89,52,245₹12.9 crore
- Current progress
- Agreement executed. Work started.Old bridge demolished.Temporary foot bridge constructed.Foundation work started.Well kerb concreting completed for two well foundation