Savakotta Bridge and Kommady Bridge
In progress71%Physical progress
68%Financial progress
Scheduled start12-11-2019
Scheduled completion31-12-2025
- Contractor
- K. J. Varghese
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹29,20,85,988₹29.21 crore
- Amount paid
- ₹18,12,62,129₹18.13 crore
- Paid to contractor
- ₹17,10,99,000₹17.11 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹35,02,71,183₹35.03 crore
- Technical sanction (TS)
- ₹30,45,43,499₹30.45 crore
- Tender amount
- ₹26,67,11,730₹26.67 crore
- Letter of acceptance (LOA)
- ₹26,67,11,730₹26.67 crore
- Current progress
- Savakotta Bridge - completed Kommady Bridge- Girder works Completed. LA fund 4.36Cr transfered to LAO on 19.02.22.19(1) on 10/03/22 Request submitted for an additional amount of 53 lakhs (Int.@12%)to KIIFB and amount not yet received19(1) Draft awar