Adoor Town Bridge
Completed100%Physical progress
91.7%Financial progress
Scheduled start09-11-2018
Scheduled completion30-11-2022
- Contractor
- A. Ibrahimkutty
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹10,09,01,293₹10.09 crore
- Amount paid
- ₹9,25,48,157₹9.25 crore
- Paid to contractor
- ₹8,66,68,527₹8.67 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹11,10,00,000₹11.1 crore
- Technical sanction (TS)
- ₹11,10,00,000₹11.1 crore
- Tender amount
- ₹10,09,01,293₹10.09 crore
- Letter of acceptance (LOA)
- ₹10,09,01,293₹10.09 crore
- Current progress
- Twin Bridge completed. 784 m of drain work completed. Retaining wall completed for 70m in bridge A side. Retaining wall of 65m completed and concreting of 2nd lift of retaining wall for a length of 24m completed in bridge B side . 2 culvert and approac