Chullimadu Bridge
In progress99.2%Physical progress
95.9%Financial progress
Scheduled start29-05-2020
Scheduled completion28-02-2025
- Contractor
- P. P. Jayaprakash
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹11,15,58,233₹11.16 crore
- Amount paid
- ₹10,69,73,335₹10.7 crore
- Paid to contractor
- ₹10,09,16,287₹10.09 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹11,16,47,134₹11.16 crore
- Technical sanction (TS)
- ₹11,16,47,134₹11.16 crore
- Tender amount
- ₹10,59,23,187₹10.59 crore
- Letter of acceptance (LOA)
- ₹10,59,23,187₹10.59 crore
- Current progress
- Work in progress. 58% completed. Foundation work completed. Substructure 2 pier caps, 2 abutment caps completed. Retaining wall construction 80% completed. Pedestal completed. 7 Girder out of 12 completed. Remaining girder work is in progress.