PWD001-37-02 Vaikom

Construction of Akkarapadam Bridge Across Moovattupuzha River in Kottayam District - Contract work

Estimated amount

₹19.15 crore

₹19,14,55,732 · ₹14.11 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: WBS Base One Approved · How we group

Location

Works (1)

Akkarapadam bridge

Completed
100%Physical progress
84.3%Financial progress
Scheduled start07-10-2022
Scheduled completion15-04-2025
Implementing agency (SPV)
KRFB
Contract amount
₹17,48,72,708₹17.49 crore
Amount paid
₹14,73,33,294₹14.73 crore
Paid to contractor
₹13,79,68,793₹13.8 crore
Financial sanction (FS)
₹19,14,55,732₹19.15 crore
Technical sanction (TS)
₹16,02,75,358₹16.03 crore
Tender amount
₹18,27,53,263₹18.28 crore
Letter of acceptance (LOA)
₹15,48,75,647₹15.49 crore
Current progress
11 (1) notification published. LoA issued to contractor dated 08.07.2022.

Money trail

Estimated amount
₹19,14,55,732₹19.15 crore
Expenditure reported
₹14,10,90,26273.7% of the estimated amount

Details

Project code
PWD001-37-02
Department
Public Works
Constituency
VaikomMLA: Smt. C. K Asha
Name as KIIFB publishes it
CONSTRUCTION OF AKKARAPADAM BRIDGE ACROSS MOOVATTUPUZHA RIVER IN KOTTAYAM DISTRICT - Contract work

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Construction of Akkarapadam Bridge Across Moovattupuzha River in Kottayam District .”.

Approved
₹19,14,55,732₹19.15 crore
Paid so far
₹15,97,33,82583.4% of the amount approved

This package

Work awarded
₹15.05 crorepaid
₹15.11 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet