Perumbalam bridge
In progress93.8%Physical progress
86.5%Financial progress
Scheduled start07-01-2021
Scheduled completion06-10-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,00,16,95,817₹100.17 crore
- Amount paid
- ₹86,68,40,386₹86.68 crore
- Paid to contractor
- ₹80,34,80,611₹80.35 crore
- Administrative sanction (AS)
- ₹1,00,00,00,000₹100 crore
- Financial sanction (FS)
- ₹1,06,07,82,126₹106.08 crore
- Technical sanction (TS)
- ₹1,00,16,95,817₹100.17 crore
- Tender amount
- ₹97,12,98,012₹97.13 crore
- Letter of acceptance (LOA)
- ₹97,12,98,012₹97.13 crore
- Current progress
- Pile 132/148,fender pile 24/24, Pile cap 29/31, Pier 68/68,Pier cap 30/36 completed.Girder work in progress.BVR approved by DC on 08/06/22.Public hearing for RR package on 19/07/22& 20/07/22