Kanakkuമലയാളം

Total of works

₹106.08 crore

₹1,06,07,82,126

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Perumbalam bridge

Scheduled completion was 06-10-2025. That was 361 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Perumbalam bridge

In progress
93.8%Physical progress
86.5%Financial progress
Scheduled start07-01-2021
Scheduled completion06-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹1,00,16,95,817₹100.17 crore
Amount paid
₹86,68,40,386₹86.68 crore
Paid to contractor
₹80,34,80,611₹80.35 crore
Administrative sanction (AS)
₹1,00,00,00,000₹100 crore
Financial sanction (FS)
₹1,06,07,82,126₹106.08 crore
Technical sanction (TS)
₹1,00,16,95,817₹100.17 crore
Tender amount
₹97,12,98,012₹97.13 crore
Letter of acceptance (LOA)
₹97,12,98,012₹97.13 crore
Current progress
Pile 132/148,fender pile 24/24, Pile cap 29/31, Pier 68/68,Pier cap 30/36 completed.Girder work in progress.BVR approved by DC on 08/06/22.Public hearing for RR package on 19/07/22& 20/07/22

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,06,07,82,126₹106.08 crore

Details

Project code
PWD001-40-01
Department
Public Works
Constituency
Aroor

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…