Total of works

₹19.43 crore

₹19,42,69,171

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Ramanchira Bridge

Scheduled completion was 31-10-2025. That was 336 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Ramanchira Bridge

In progress
95%Physical progress
81.7%Financial progress
Scheduled start23-02-2023
Scheduled completion31-10-2025
Contractor
Sreekantan Nair
Implementing agency (SPV)
KRFB
Contract amount
₹17,69,33,700₹17.69 crore
Amount paid
₹14,45,31,408₹14.45 crore
Paid to contractor
₹13,65,69,892₹13.66 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹19,42,69,171₹19.43 crore
Technical sanction (TS)
₹16,25,20,000₹16.25 crore
Tender amount
₹17,69,34,227₹17.69 crore
Current progress
Financial bid opened.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹19,42,69,171₹19.43 crore

Details

Project code
PWD001-43-02
Department
Public Works
Constituency
Trikaripur

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026