Total of works

₹34.32 crore

₹34,31,78,647

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Malampuzha Ring Road Bridge

Scheduled completion was 17-03-2025. That was 564 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Malampuzha Ring Road Bridge

In progress
60%Physical progress
60.4%Financial progress
Scheduled start18-03-2022
Scheduled completion17-03-2025
Implementing agency (SPV)
KRFB
Contract amount
₹42,29,67,192₹42.3 crore
Amount paid
₹25,54,90,481₹25.55 crore
Paid to contractor
₹24,13,21,436₹24.13 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹34,31,78,647₹34.32 crore
Technical sanction (TS)
₹34,31,70,000₹34.32 crore
Tender amount
₹42,29,67,192₹42.3 crore
Letter of acceptance (LOA)
₹37,76,49,278₹37.76 crore
Current progress
Agreement executed on 09.03.22 work started at site. Work inaugurated by Minister on 04.04.2022. Foundation work in progress at P2(pile 38no.s completed) . Pile caps constructed at P3, P4,P5 and P6. Pier construction work in progress. Confirmatory boring

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹34,31,78,647₹34.32 crore

Details

Project code
PWD001-44-01
Department
Public Works
Constituency
Malampuzha

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026