Malampuzha Ring Road Bridge
In progress60%Physical progress
60.4%Financial progress
Scheduled start18-03-2022
Scheduled completion17-03-2025
- Contractor
- T. A. Abdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹42,29,67,192₹42.3 crore
- Amount paid
- ₹25,54,90,481₹25.55 crore
- Paid to contractor
- ₹24,13,21,436₹24.13 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹34,31,78,647₹34.32 crore
- Technical sanction (TS)
- ₹34,31,70,000₹34.32 crore
- Tender amount
- ₹42,29,67,192₹42.3 crore
- Letter of acceptance (LOA)
- ₹37,76,49,278₹37.76 crore
- Current progress
- Agreement executed on 09.03.22 work started at site. Work inaugurated by Minister on 04.04.2022. Foundation work in progress at P2(pile 38no.s completed) . Pile caps constructed at P3, P4,P5 and P6. Pier construction work in progress. Confirmatory boring