Kanakkuമലയാളം

Total of works

₹23.32 crore

₹23,32,04,455

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Moolekkadavu bridge

Scheduled completion was 31-01-2026. That was 244 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Moolekkadavu bridge

In progress
76.7%Physical progress
64.8%Financial progress
Scheduled start05-12-2022
Scheduled completion31-01-2026
Contractor
KTMathew&Co.
Implementing agency (SPV)
KRFB
Contract amount
₹22,27,95,417₹22.28 crore
Amount paid
₹14,43,58,022₹14.44 crore
Paid to contractor
₹13,51,82,674₹13.52 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹23,32,04,455₹23.32 crore
Technical sanction (TS)
₹22,27,95,417₹22.28 crore
Tender amount
₹21,14,79,097₹21.15 crore
Letter of acceptance (LOA)
₹18,88,20,623₹18.88 crore
Current progress
Work tendered and selection notice to be issued. Contingency charge of 2 lakh have been handed over to Tahsildar(LA KIIFB Vaikom).Revised recquisition submitted. Request submitted for revised revenue B sanction. 4 (1) Notification Published & Agency for

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹23,32,04,455₹23.32 crore

Details

Project code
PWD001-49-02
Department
Public Works
Constituency
Vaikom

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…