Moolekkadavu bridge
In progress76.7%Physical progress
64.8%Financial progress
Scheduled start05-12-2022
Scheduled completion31-01-2026
- Contractor
- KTMathew&Co.
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹22,27,95,417₹22.28 crore
- Amount paid
- ₹14,43,58,022₹14.44 crore
- Paid to contractor
- ₹13,51,82,674₹13.52 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹23,32,04,455₹23.32 crore
- Technical sanction (TS)
- ₹22,27,95,417₹22.28 crore
- Tender amount
- ₹21,14,79,097₹21.15 crore
- Letter of acceptance (LOA)
- ₹18,88,20,623₹18.88 crore
- Current progress
- Work tendered and selection notice to be issued. Contingency charge of 2 lakh have been handed over to Tahsildar(LA KIIFB Vaikom).Revised recquisition submitted. Request submitted for revised revenue B sanction. 4 (1) Notification Published & Agency for