Kanjirapally Bypass
In progress34%Physical progress
23.4%Financial progress
Scheduled start10-08-2023
Scheduled completion30-06-2025
- Contractor
- Backbone Construction Pvt Ltd
- Implementing agency (SPV)
- RBDCK
- Contract amount
- ₹30,87,76,115₹30.88 crore
- Amount paid
- ₹7,22,93,436₹7.23 crore
- Paid to contractor
- ₹6,76,98,511₹6.77 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹78,69,45,144₹78.69 crore
- Technical sanction (TS)
- ₹33,54,05,116₹33.54 crore
- Tender amount
- ₹30,87,76,115₹30.88 crore
- Letter of acceptance (LOA)
- ₹26,16,74,674₹26.17 crore
- Current progress
- LA requisition submitted on 29.08.2018. Land taken possession started on 06.05.2022. 99% LA completed. Tahsildar agreed to complete the acquisition of balance land within two months. Permission to tender the work received from GoK on 25.06.2022. TS Commi