Total of works

₹78.69 crore

₹78,69,45,144

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kanjirapally Bypass

Scheduled completion was 30-06-2025. That was 459 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kanjirapally Bypass

In progress
34%Physical progress
23.4%Financial progress
Scheduled start10-08-2023
Scheduled completion30-06-2025
Implementing agency (SPV)
RBDCK
Contract amount
₹30,87,76,115₹30.88 crore
Amount paid
₹7,22,93,436₹7.23 crore
Paid to contractor
₹6,76,98,511₹6.77 crore
Administrative sanction (AS)
₹20,00,00,000₹20 crore
Financial sanction (FS)
₹78,69,45,144₹78.69 crore
Technical sanction (TS)
₹33,54,05,116₹33.54 crore
Tender amount
₹30,87,76,115₹30.88 crore
Letter of acceptance (LOA)
₹26,16,74,674₹26.17 crore
Current progress
LA requisition submitted on 29.08.2018. Land taken possession started on 06.05.2022. 99% LA completed. Tahsildar agreed to complete the acquisition of balance land within two months. Permission to tender the work received from GoK on 25.06.2022. TS Commi

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹78,69,45,144₹78.69 crore

Details

Project code
PWD003-03-02
Department
Public Works
Constituency
Kanjirappally

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026