Kalpetta - Varambetta Road
Foreclosed92%Physical progress
77.5%Financial progress
Scheduled start24-10-2018
Scheduled completion30-09-2024
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹55,53,03,572₹55.53 crore
- Amount paid
- ₹43,01,29,517₹43.01 crore
- Paid to contractor
- ₹39,77,99,893₹39.78 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹57,91,02,407₹57.91 crore
- Technical sanction (TS)
- ₹55,53,03,572₹55.53 crore
- Tender amount
- ₹51,63,27,674₹51.63 crore
- Letter of acceptance (LOA)
- ₹51,63,27,674₹51.63 crore
- Current progress
- Balance concrete works ( retaining wall) as per RE started. GSB, WMM, DBM completed in the 17.725 km. BC to be started.