Meppadi - Chooralmala Road
In progress35%Physical progress
23.5%Financial progress
Scheduled start17-02-2024
Scheduled completion31-12-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹33,97,55,966₹33.98 crore
- Amount paid
- ₹7,98,62,380₹7.99 crore
- Paid to contractor
- ₹7,47,86,342₹7.48 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹50,15,81,797₹50.16 crore
- Technical sanction (TS)
- ₹31,37,30,000₹31.37 crore
- Tender amount
- ₹33,97,55,966₹33.98 crore
- Current progress
- On 22.06.2021 KIIFB issued Stop memo to the work. 50% of total work is completed. Total length of the road is 12.8 km. DBM completed for 5.5km. Land not available in the reamaining 6.2 km stretch. Out of the 25 culverts, 15 completed.Work to b