Total of works

₹50.16 crore

₹50,15,81,797

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Meppadi - Chooralmala Road

Scheduled completion was 31-12-2025. That was 275 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Meppadi - Chooralmala Road

In progress
35%Physical progress
23.5%Financial progress
Scheduled start17-02-2024
Scheduled completion31-12-2025
Implementing agency (SPV)
KRFB
Contract amount
₹33,97,55,966₹33.98 crore
Amount paid
₹7,98,62,380₹7.99 crore
Paid to contractor
₹7,47,86,342₹7.48 crore
Administrative sanction (AS)
₹15,00,00,000₹15 crore
Financial sanction (FS)
₹50,15,81,797₹50.16 crore
Technical sanction (TS)
₹31,37,30,000₹31.37 crore
Tender amount
₹33,97,55,966₹33.98 crore
Current progress
On 22.06.2021 KIIFB issued Stop memo to the work. 50% of total work is completed. Total length of the road is 12.8 km. DBM completed for 5.5km. Land not available in the reamaining 6.2 km stretch. Out of the 25 culverts, 15 completed.Work to b

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹50,15,81,797₹50.16 crore

Details

Project code
PWD004-103-03
Department
Public Works
Constituency
Kalpetta

What we don't know yet