Vaikom Vechoor Road
Completed100%Physical progress
88.2%Financial progress
Scheduled start22-10-2020
Scheduled completion31-10-2025
- Contractor
- Asharaf. T. A
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹3,76,90,372₹3.77 crore
- Amount paid
- ₹3,32,60,264₹3.33 crore
- Paid to contractor
- ₹3,13,57,016₹3.14 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹1,56,99,37,600₹156.99 crore
- Technical sanction (TS)
- ₹3,76,90,372₹3.77 crore
- Tender amount
- ₹4,01,55,377₹4.02 crore
- Letter of acceptance (LOA)
- ₹4,01,55,377₹4.02 crore
- Current progress
- Bridge: Part TS issued to Anjumana bridge. Work in progress. Construction of suprerstructure completed.Necessary action has been taken to cut the two trees which are hindrance to KSEB utility shifting.RR work for the retaining wall on vaikom side complet