Total of works

₹63.99 crore

₹63,99,00,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Flags (1)

Payment ahead of progress · Erattupetta-Vagamon Road

Reported financial progress is 81% and reported physical progress is 0%, a gap of 81 points.

Rule: Reported financial progress is 25 or more percentage points ahead of reported physical progress. Rule version 2 · Since 30-09-2026

Works (1)

Erattupetta-Vagamon Road

Approved
0%Physical progress
81%Financial progress
Contractor
Not published
Implementing agency (SPV)
RICK
Contract amount
Not published
Amount paid
₹25,00,000₹25 lakh
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹63,99,00,000₹63.99 crore
Technical sanction (TS)
₹31,00,000₹31 lakh
Current progress
4(1) to be published by Revenue Department

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹63,99,00,000₹63.99 crore

Details

Project code
PWD004-113
Department
Public Works
Executing agency
RICK
Constituency
Alappuzha

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Erattupetta-Vagamon Road
  • Scheduled start and completion dates · Erattupetta-Vagamon Road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026