Kanakkuമലയാളം

Total of works

₹32.89 crore

₹32,89,00,000

Stage

Approved

Status of the works, as KIIFB records it.

Location

Works (1)

Kazhani Pazhambalacode Road

Approved
0%Physical progress
0%Financial progress
Contractor
Not published
Implementing agency (SPV)
KRFB
Contract amount
Not published
Amount paid
Not published
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹32,89,00,000₹32.89 crore
Current progress
Deferred

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹32,89,00,000₹32.89 crore

Details

Project code
PWD004-124
Department
Public Works
Constituency
Tarur

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Contractor · Kazhani Pazhambalacode Road
  • Scheduled start and completion dates · Kazhani Pazhambalacode Road
  • Amount paid · Kazhani Pazhambalacode Road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…