Nileshwar-Edathode road
Terminated83.5%Physical progress
31.1%Financial progress
Scheduled start28-02-2019
Scheduled completion30-06-2023
- Contractor
- KMoideenkutty Haji
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹29,59,47,717₹29.59 crore
- Amount paid
- ₹9,20,83,679₹9.21 crore
- Paid to contractor
- ₹8,41,90,469₹8.42 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹43,26,67,784₹43.27 crore
- Technical sanction (TS)
- ₹25,91,000₹25.91 lakh
- Tender amount
- ₹29,59,47,717₹29.59 crore
- Letter of acceptance (LOA)
- ₹29,59,47,717₹29.59 crore
- Current progress
- Time of completion end on to 30/06/2022. EOT sought up to 28.02.2023.DBM layed from Km 2/525 to 2/710, 4/720 to 5/030, 5/030 to7/392, 7/392 to 7/500 & 8/310 to 12/595. (Total completed DBM length=7.25Km).CC protection work in progress.Precast drain layin