PWD004-128-01 Kanhangad

Improvements to Nileshwar- Edathode road - Contract work

Estimated amount

₹58.93 crore

₹58,93,47,735 · ₹8.85 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Works (1)

Nileshwar-Edathode road

Terminated
83.5%Physical progress
31.1%Financial progress
Scheduled start28-02-2019
Scheduled completion30-06-2023
Implementing agency (SPV)
KRFB
Contract amount
₹29,59,47,717₹29.59 crore
Amount paid
₹9,20,83,679₹9.21 crore
Paid to contractor
₹8,41,90,469₹8.42 crore
Administrative sanction (AS)
₹25,00,00,000₹25 crore
Financial sanction (FS)
₹43,26,67,784₹43.27 crore
Technical sanction (TS)
₹25,91,000₹25.91 lakh
Tender amount
₹29,59,47,717₹29.59 crore
Letter of acceptance (LOA)
₹29,59,47,717₹29.59 crore
Current progress
Time of completion end on to 30/06/2022. EOT sought up to 28.02.2023.DBM layed from Km 2/525 to 2/710, 4/720 to 5/030, 5/030 to7/392, 7/392 to 7/500 & 8/310 to 12/595. (Total completed DBM length=7.25Km).CC protection work in progress.Precast drain layin

Money trail

Estimated amount
₹58,93,47,735₹58.93 crore
Expenditure reported
₹8,84,74,63715% of the estimated amount

Details

Project code
PWD004-128-01
Department
Public Works
Constituency
Kanhangad

What we don't know yet