Mananthavady Kaithakkal Road
Completed100%Physical progress
88.5%Financial progress
Scheduled start13-11-2018
Scheduled completion30-06-2025
- Contractor
- M/s Ernad Engineering Enterprises
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹42,30,02,335₹42.3 crore
- Amount paid
- ₹37,43,93,041₹37.44 crore
- Paid to contractor
- ₹34,63,49,384₹34.63 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore