Beenachi - Panamaram Road
In progress74.6%Physical progress
52.8%Financial progress
Scheduled start25-01-2024
Scheduled completion24-07-2025
- Contractor
- K. Muhammed Haji
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹32,90,04,013₹32.9 crore
- Amount paid
- ₹17,38,04,571₹17.38 crore
- Paid to contractor
- ₹16,42,30,588₹16.42 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹72,19,49,167₹72.19 crore
- Technical sanction (TS)
- ₹32,56,00,000₹32.56 crore
- Tender amount
- ₹32,90,04,013₹32.9 crore
- Current progress
- On 16.09.2021 files received from PWD roads wayanad. Project scope has been changed from 22km to 12.86km for the present agency by PD as per the instruction from KIIFB. DBM completed for 11.71 km in the revised scope.DR works and shoulder filling works