Ottapalam- Perithalmanna road
Foreclosed88%Physical progress
67.2%Financial progress
Scheduled start19-04-2020
Scheduled completion19-04-2022
- Contractor
- T. AAbdul Rahiman
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹20,83,77,471₹20.84 crore
- Amount paid
- ₹14,64,31,967₹14.64 crore
- Paid to contractor
- ₹13,79,33,661₹13.79 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹28,33,00,000₹28.33 crore
- Technical sanction (TS)
- ₹21,79,98,674₹21.8 crore
- Tender amount
- ₹20,83,77,471₹20.84 crore
- Letter of acceptance (LOA)
- ₹20,83,77,471₹20.84 crore
- Current progress
- Presently First layer taring, DBM completed in full length. drain works and retaining wall works are 90% completed.BC Laying planned after rainy season.Total project completion is 88%