Total of works

₹178.24 crore

₹1,78,24,26,656

Stage

Completed

Status of the works, as KIIFB records it.

Location

Works (1)

Udumbanchola-Rajakkadu road

Completed
100%Physical progress
98.1%Financial progress
Scheduled start22-02-2020
Scheduled completion31-12-2024
Implementing agency (SPV)
KRFB
Contract amount
₹1,72,08,82,654₹172.09 crore
Amount paid
₹1,68,80,74,853₹168.81 crore
Paid to contractor
₹1,57,90,81,403₹157.91 crore
Administrative sanction (AS)
₹35,00,00,000₹35 crore
Financial sanction (FS)
₹1,78,24,26,656₹178.24 crore
Technical sanction (TS)
₹1,76,25,17,280₹176.25 crore
Tender amount
₹1,56,68,81,204₹156.69 crore
Letter of acceptance (LOA)
₹1,56,68,81,204₹156.69 crore
Current progress
Work started on 22-02-2020. Work handed over to KRFB on 26/08/2021. GSB,WMM,DBM,BC,Retaining wall and culvert work in progress, 3 Nos Bridge work completed upto top slab . Overall Progress is 50%. KSEB & KWA utility shifting work is ongoing. Time of c

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹1,78,24,26,656₹178.24 crore

Details

Project code
PWD004-147-01
Department
Public Works
Constituency
Udumbanchola

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…