Udumbanchola-Rajakkadu road
Completed100%Physical progress
98.1%Financial progress
Scheduled start22-02-2020
Scheduled completion31-12-2024
- Contractor
- M/s EKKInfrastructure Limited
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹1,72,08,82,654₹172.09 crore
- Amount paid
- ₹1,68,80,74,853₹168.81 crore
- Paid to contractor
- ₹1,57,90,81,403₹157.91 crore
- Administrative sanction (AS)
- ₹35,00,00,000₹35 crore
- Financial sanction (FS)
- ₹1,78,24,26,656₹178.24 crore
- Technical sanction (TS)
- ₹1,76,25,17,280₹176.25 crore
- Tender amount
- ₹1,56,68,81,204₹156.69 crore
- Letter of acceptance (LOA)
- ₹1,56,68,81,204₹156.69 crore
- Current progress
- Work started on 22-02-2020. Work handed over to KRFB on 26/08/2021. GSB,WMM,DBM,BC,Retaining wall and culvert work in progress, 3 Nos Bridge work completed upto top slab . Overall Progress is 50%. KSEB & KWA utility shifting work is ongoing. Time of c