Podiyadi- Thiruvalla road
Completed100%Physical progress
100%Financial progress
Scheduled start04-11-2020
Scheduled completion31-10-2023
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹53,64,15,278₹53.64 crore
- Amount paid
- ₹53,62,31,571₹53.62 crore
- Paid to contractor
- ₹50,09,11,245₹50.09 crore
- Administrative sanction (AS)
- ₹56,00,00,000₹56 crore
- Financial sanction (FS)
- ₹77,36,03,908₹77.36 crore
- Technical sanction (TS)
- ₹53,59,32,612₹53.59 crore
- Tender amount
- ₹53,11,33,000₹53.11 crore
- Letter of acceptance (LOA)
- ₹53,11,33,000₹53.11 crore
- Current progress
- STRETCH 1 - Tile work of 100mm is completed upto 90%. Embankment work is also completed upto 85% with geotextile. Retaining wall works are also under progress. Drain works also in progress. STRETCH 2 - Drain is completed upto 98%, almost 100 m pending.