Kaithavana Vadakkenada Road
In progress90%Physical progress
Not publishedFinancial progress
Scheduled start31-03-2025
Scheduled completion15-10-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹2,29,40,174₹2.29 crore
- Amount paid
- Not published
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹20,37,73,195₹20.38 crore
- Technical sanction (TS)
- ₹1,69,30,924₹1.69 crore
- Tender amount
- ₹2,29,40,174₹2.29 crore
- Current progress
- Culvert work ,Drainage works &BM completed. BC completed except 1.5km.Fund for Utility shifting of KSEB transferred to Corresponding KSEB sections on 22/03/22 and tendered .RE @ 7.08% placed in 100th TS committee and forward to KIIFB for approval on 29/