Total of works

₹20.38 crore

₹20,37,73,195

Stage

In progress

Status of the works, as KIIFB records it.

Location

Flags (1)

Overdue · Kaithavana Vadakkenada Road

Scheduled completion was 15-10-2025. That was 352 days ago, and KIIFB lists the status as “Inprogress”.

Rule: Today is past the scheduled completion date and KIIFB does not list the work as ended (Completed, Foreclosed, Terminated or Package Disposed). Rule version 2 · Since 30-09-2026

Works (1)

Kaithavana Vadakkenada Road

In progress
90%Physical progress
Not publishedFinancial progress
Scheduled start31-03-2025
Scheduled completion15-10-2025
Implementing agency (SPV)
KRFB
Contract amount
₹2,29,40,174₹2.29 crore
Amount paid
Not published
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹20,37,73,195₹20.38 crore
Technical sanction (TS)
₹1,69,30,924₹1.69 crore
Tender amount
₹2,29,40,174₹2.29 crore
Current progress
Culvert work ,Drainage works &BM completed. BC completed except 1.5km.Fund for Utility shifting of KSEB transferred to Corresponding KSEB sections on 22/03/22 and tendered .RE @ 7.08% placed in 100th TS committee and forward to KIIFB for approval on 29/

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹20,37,73,195₹20.38 crore

Details

Project code
PWD004-25-05
Department
Public Works
Constituency
Alappuzha

What we don't know yet

The KIIFB dashboard does not publish these for this project:

  • Amount paid · Kaithavana Vadakkenada Road

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026