Hosdurg-Panathur road
In progress66%Physical progress
51.9%Financial progress
Scheduled start13-04-2022
Scheduled completion31-12-2025
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹52,98,09,435₹52.98 crore
- Amount paid
- ₹27,50,47,641₹27.5 crore
- Paid to contractor
- ₹25,75,65,780₹25.76 crore
- Administrative sanction (AS)
- ₹35,00,00,000₹35 crore
- Financial sanction (FS)
- ₹62,01,28,716₹62.01 crore
- Technical sanction (TS)
- ₹59,94,00,000₹59.94 crore
- Tender amount
- ₹52,98,09,435₹52.98 crore
- Letter of acceptance (LOA)
- ₹47,30,44,139₹47.3 crore
- Current progress
- TS Issued vide order.No.PWD/KR/EST TS/94589/2021 5 1 Dated:25.08.2021 For Rs.59.94Crores. Tender opened. LMR Justification submitted.