Manjinikkara - Elavummthitta- Road
Foreclosed82%Physical progress
49.4%Financial progress
Scheduled start08-02-2019
Scheduled completion30-07-2022
- Contractor
- M/s Rajesh Mathewand Company
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹23,70,84,103₹23.71 crore
- Amount paid
- ₹11,70,21,601₹11.7 crore
- Paid to contractor
- ₹10,85,21,318₹10.85 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹24,33,00,000₹24.33 crore
- Technical sanction (TS)
- ₹24,17,00,000₹24.17 crore
- Tender amount
- ₹23,70,84,103₹23.71 crore
- Letter of acceptance (LOA)
- ₹22,99,61,773₹23 crore
- Current progress
- 99% of DBM completed and BC completed in 4km. 21 culverts were completed out of 22 nos. DGBM completed in 2nd reach also. RE placed in TS Committee direction has been given to contractor to execute supplimentary agreement. PD has agreed to conduct a