Changanassery-Kaviyoor-Thottabhagom road
Foreclosed96%Physical progress
91.9%Financial progress
Scheduled start26-11-2018
Scheduled completion30-04-2022
- Contractor
- Theruvath Builders
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹29,54,46,613₹29.54 crore
- Amount paid
- ₹27,14,25,448₹27.14 crore
- Paid to contractor
- ₹25,12,17,077₹25.12 crore
- Financial sanction (FS)
- ₹48,30,04,333₹48.3 crore
- Technical sanction (TS)
- ₹32,76,00,000₹32.76 crore
- Tender amount
- ₹29,54,46,613₹29.54 crore
- Letter of acceptance (LOA)
- ₹29,54,46,613₹29.54 crore
- Current progress
- BM works completed. Land Acquisition is not possible between Payippad and Perunna. KWA utility shifting completed. Letter has been sent to the Prjoect Director for giving instruction to Contractor for resuming the work. But the Contractor has not yet re