Muthoor-Kuttoor-Kizakkan Muthoor Road
Completed100%Physical progress
98.8%Financial progress
Scheduled start24-10-2018
Scheduled completion04-08-2022
- Contractor
- M/s Palathara Constructions
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹28,59,75,035₹28.6 crore
- Amount paid
- ₹28,02,78,822₹28.03 crore
- Paid to contractor
- ₹25,94,18,553₹25.94 crore
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹29,89,76,627₹29.9 crore
- Technical sanction (TS)
- ₹28,79,48,473₹28.79 crore
- Tender amount
- ₹23,51,50,033₹23.52 crore
- Letter of acceptance (LOA)
- ₹23,51,50,033₹23.52 crore
- Current progress
- Work completed.