PWD004-69-01 Thiruvalla

Muthoor - Kuttoor - Kizhakkan Muthoor road- Contract work

Estimated amount

₹29.9 crore

₹29,89,76,627 · ₹26.64 crore spent

Stage

  1. Preparation
  2. Technical sanction
  3. Tender
  4. Contract
  5. Work plan

KIIFB status: Contract Process Completed · How we group

Location

Works (1)

Muthoor-Kuttoor-Kizakkan Muthoor Road

Completed
100%Physical progress
98.8%Financial progress
Scheduled start24-10-2018
Scheduled completion04-08-2022
Implementing agency (SPV)
KRFB
Contract amount
₹28,59,75,035₹28.6 crore
Amount paid
₹28,02,78,822₹28.03 crore
Paid to contractor
₹25,94,18,553₹25.94 crore
Administrative sanction (AS)
₹10,00,00,000₹10 crore
Financial sanction (FS)
₹29,89,76,627₹29.9 crore
Technical sanction (TS)
₹28,79,48,473₹28.79 crore
Tender amount
₹23,51,50,033₹23.52 crore
Letter of acceptance (LOA)
₹23,51,50,033₹23.52 crore
Current progress
Work completed.

Money trail

Estimated amount
₹29,89,76,627₹29.9 crore
Expenditure reported
₹26,64,25,52889.1% of the estimated amount

Details

Project code
PWD004-69-01
Department
Public Works
Constituency
ThiruvallaMLA: Shri Mathew. T. Thomas

What KIIFB approved and paid

On KIIFB's project status page this belongs to “Improvements and providing BM & BC to Muthoor - Kuttoor - Kizhakkan Muthoor road”.

Approved
₹29,89,76,627₹29.9 crore
Paid so far
₹29,33,20,22398.1% of the amount approved

This package

Work awarded
₹28.03 crorepaid
₹28.6 croreapproved

Source: KIIFB project status (kiifb.org). Checked 02-10-2026. How we joined the two sources

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026