Elenjimel-Harippad Road
Completed100%Physical progress
99.8%Financial progress
Scheduled start31-01-2018
Scheduled completion03-07-2023
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹15,35,50,269₹15.36 crore
- Amount paid
- ₹15,32,49,480₹15.32 crore
- Paid to contractor
- ₹14,28,67,144₹14.29 crore
- Administrative sanction (AS)
- ₹15,00,00,000₹15 crore
- Financial sanction (FS)
- ₹16,66,00,000₹16.66 crore
- Technical sanction (TS)
- ₹15,35,50,269₹15.36 crore
- Tender amount
- ₹14,35,26,866₹14.35 crore
- Letter of acceptance (LOA)
- ₹14,35,26,866₹14.35 crore
- Current progress
- Tech Committee on3/3/2022. RE to be resubmitted after rechecking the rate analysis of coconut piles re resubmitted after correction to PD