Total of works

₹20.24 crore

₹20,24,00,000

Stage

Foreclosed

Status of the works, as KIIFB records it.

Location

Works (1)

Bhagavathyppadi - Mallikkattu Ferry road

Foreclosed
96%Physical progress
99.6%Financial progress
Scheduled start25-06-2018
Scheduled completion14-08-2025
Implementing agency (SPV)
KRFB
Contract amount
₹15,93,20,509₹15.93 crore
Amount paid
₹15,86,59,272₹15.87 crore
Paid to contractor
₹14,67,59,785₹14.68 crore
Administrative sanction (AS)
₹20,00,00,000₹20 crore
Financial sanction (FS)
₹20,24,00,000₹20.24 crore
Technical sanction (TS)
₹20,06,00,000₹20.06 crore
Tender amount
₹19,10,26,842₹19.1 crore
Letter of acceptance (LOA)
₹19,10,26,842₹19.1 crore
Current progress
BC, BM, drainage, protection works are completed. Road safety work completed. KWA ,KSEB & BSNL utilities shifted near pathiyoor bridge.

Money trail

Estimated amount
Not published
Expenditure reported
Not published
Total of works
₹20,24,00,000₹20.24 crore

Details

Project code
PWD004-93-01
Department
Public Works
Constituency
Kayamkulam

What we don't know yet

The dashboard publishes every field we check.

Source

Source
KIIFB integrated dashboardgis.kiifb.org
Retrieved
30-09-2026
First recorded
30-09-2026
SHA-256
04a00101b9212117…