Bhagavathyppadi - Mallikkattu Ferry road
Foreclosed96%Physical progress
99.6%Financial progress
Scheduled start25-06-2018
Scheduled completion14-08-2025
- Contractor
- K. V. Jacob&Sons
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹15,93,20,509₹15.93 crore
- Amount paid
- ₹15,86,59,272₹15.87 crore
- Paid to contractor
- ₹14,67,59,785₹14.68 crore
- Administrative sanction (AS)
- ₹20,00,00,000₹20 crore
- Financial sanction (FS)
- ₹20,24,00,000₹20.24 crore
- Technical sanction (TS)
- ₹20,06,00,000₹20.06 crore
- Tender amount
- ₹19,10,26,842₹19.1 crore
- Letter of acceptance (LOA)
- ₹19,10,26,842₹19.1 crore
- Current progress
- BC, BM, drainage, protection works are completed. Road safety work completed. KWA ,KSEB & BSNL utilities shifted near pathiyoor bridge.