Vadanamkurussi Railway Over Bridge
Completed100%Physical progress
100%Financial progress
- Contractor
- Not published
- Implementing agency (SPV)
- RBDCK
- Contract amount
- Not published
- Amount paid
- ₹11,02,150₹11.02 lakh
- Administrative sanction (AS)
- ₹10,00,00,000₹10 crore
- Financial sanction (FS)
- ₹5,34,99,000₹5.35 crore
- Current progress
- Piling works completed (Excluding railway portion). 14/15 pile cap completed. 10/13 pier & pier cap completed. Fabrication of 3 Pier cap completed at Fabrication yard. Pedestrain under pass work is in progress