Madathumchal- Mukkoottuthara road
In progress23.5%Physical progress
16.5%Financial progress
Scheduled start26-01-2025
Scheduled completion25-01-2026
- Implementing agency (SPV)
- KRFB
- Contract amount
- ₹19,51,68,377₹19.52 crore
- Amount paid
- ₹3,22,12,156₹3.22 crore
- Paid to contractor
- ₹3,01,64,773₹3.02 crore
- Administrative sanction (AS)
- ₹25,00,00,000₹25 crore
- Financial sanction (FS)
- ₹51,65,01,000₹51.65 crore
- Technical sanction (TS)
- ₹17,75,40,000₹17.75 crore
- Tender amount
- ₹19,51,68,377₹19.52 crore
- Current progress
- DBM completed for the entire stretch. BC - 5.8 km completed. As per direction of CEO, this work has been foreclosed. Estimate for the remaining work submitted to PD, KRFB. NOC received from EE, KSEB. KWA restoration is nearing completion.